The project began immediately after Easter with the delivery of two of our FLEXWELL DHC pipes in the largest available dimension DN 150, which weighed an impressive 7.5 tons per pipe. With a casing diameter of 310 millimetres, a pipe length of 226 meters each was transported to Bern on two drums. Thanks to the use of a special transport with extra width, the pipes were also transported over narrow stretches of land.
The construction site was managed thanks to the use of heavy machinery and six experienced fitters. A special mobile crane with a lifting capacity of 130 tons was used to unload the pipes. Another 60-tonne pneumatic crane lifted the drums into the pipe-laying trolley. Two of the FLEXWELL DHC district heating pipes were pulled from the starting trench on Arastrasse in Ittigen into the empty pipes and laid from there under the river up to Tiefenaustrasse in Bern using cable winches.
We would like to thank our partners EQUANS, Durena AG and Ryser Ingenieure AG for their excellent cooperation and our customer EBL for this exciting contract. Together we are driving sustainable energy supply forward.